SAMPLE ONLY. Invented for the CCAZ AI at Work session. Ready-mix account terms (summary) - Orders placed by 2:00p the business day before. Friday 2:00p for Monday. - Orders cancelled inside 24 hours of first load are charged a short-load and cancellation fee per the account terms. - Truck spacing: 3 trucks rotating for anything over 150 CY; 2 trucks under 150 CY. - 4000 psi structural mix. Flatwork mix has a different slump; confirm mix ID on the order. Pump (rented with operator) - Book 48 hours ahead. Same-day changes depend on availability, no guarantee. - Anything over 150 CY or any elevated deck: line pump minimum, boom preferred. - Elevated deck over 200 CY: two pumps. - Columns: small pump. House rules - One foreman per active pour. The float foreman covers forming days. - Finishers stay on a slab until saw cuts. Do not pull finishers off a slab pour before 2:00p to start another. - New hires do not run the screed or the pump hose in their first 30 days. - Light duty means no pour work.